Kiran Gholap
29th May 2008, 16:56
Plaese advise us how to deal with parallel operations. Refer below business situation. In production planning we have 5 operations numbered as 10,20....50. We want to complete operation 30 without completing operations 10 and 20 i.e. we want to complete operations independently. Please note that all these operations belong to same routing and not to phantom routing (network routing) and we dont want to use "operation relationship by production order". because this does not satisfy our requirement in case different quantities are to be completed for different operations. Also this requires manual rescheduling of operations.
Please advise on this.
Regards
Kiran Gholap
Please advise on this.
Regards
Kiran Gholap