riazsayeed
27th December 2007, 08:35
Hi folks,

LN 6.1
------

I have many Production orders with status Closed, I get the following in the WIP report for the same:

Eg:

Incoming WIP value : 433508.75
Booked results : - 85137.59
Outgoing WIP value : 350199.36
Amount WIP : -1828.19

My doubt is: Should not the WIP become zero when we close the Prduction order?

Any help would be highly appreciated.

Thanks and Best Regards