metropoj
19th December 2007, 15:19
We set up our Generic Routing by the unit ordered.
At some point, it was decided that for some "Operations" under Maintain Generic Routing, the "Setup" field would be used to represent the setup of ONE unit. It appears as though the company would like to account for this setup time PER UNIT ordered.
For example, 1 Rail operation had a setup time of 30 minutes. IF the customer Ordered 2 rails, they want to account for 60 min setup time, 30 min per rail unit.
I know that 'run_time' or 'quantity' allows me in the constraints to access the 'Run Time' or 'Quantity' field from the operations.
Is anyone familiar if I can use the variable 'setup' in constraint program to read that value from the 'Setup' routing operations ?
I hope that was clear ?
At some point, it was decided that for some "Operations" under Maintain Generic Routing, the "Setup" field would be used to represent the setup of ONE unit. It appears as though the company would like to account for this setup time PER UNIT ordered.
For example, 1 Rail operation had a setup time of 30 minutes. IF the customer Ordered 2 rails, they want to account for 60 min setup time, 30 min per rail unit.
I know that 'run_time' or 'quantity' allows me in the constraints to access the 'Run Time' or 'Quantity' field from the operations.
Is anyone familiar if I can use the variable 'setup' in constraint program to read that value from the 'Setup' routing operations ?
I hope that was clear ?