flysurfing
30th November 2007, 10:07
Dear all,

can you tell how LN 6.1 can arrange production plan according to production capacity ?

The company in charge of the implementation of our ERP tell us we cannot manage production plan according production capacity.

They said in LN 6.1 the default value is unlimited production.

They tell us to buy the Scheduler.

Can you confirm this ?

Thanks a lot for your help !

Fly

avpatil
30th November 2007, 14:24
This is true. The default planning is based on infinite capacity. You will need to by constrain planning software on top of it.

Arvind Patil

David Eagar
30th November 2007, 21:07
Has the 5c capacity facilities been discontinued in Ln? If so, a bad move

flysurfing
3rd December 2007, 02:42
Thanks Both for your answer,

do you know how could i manage the production according to capacity in LN 6.1 ?

Should i use any third party software or do some special settings in the ERP ?

Thanks a lot for that !

Fly