jimouyang
27th August 2007, 04:17
how to backflush (see the attachment). situation :

production order status: completed
main item deliveried, ordered,initial: 1
component item estimated: 1
component item subsequent delivery: 1
issue method: selected
direct process selected
main item and component item backflush if material: selected
main item and component item backflush material: selected
main item: without rounting
SFC backflushing method: interactive

causes:

report production order complete using globally complete(tisfc0206m000),

now

how to issue component item from WIP to WC if I have stock globally. I know if deselecting <backflushing> in issue method in ticst0101s000, initiate inventory issue(tisfc0207m000) works as a rang of production. However, I have to deselect one by one. Anyone has idea how to do it in a easy way.

thank you. -jim

tomlbacon
30th August 2007, 22:29
You need to make sure that the Inventory to Backflush is in the warehouse call for in the Production Order. If Backflushing is setup correctly when you complete the Operations it should backflush the material for that Operation.