achavezf
25th May 2007, 00:44
Hi,
We are using routings (costing, man power) for our assemblies and lead times for the purchase items.
When we run the Generate Order Planning (MRP) the system takes in consideration the lead time of the supplier plus the production of the routing. I know this is normal.
The problem is as follows:
Suppose I have an end item A with a production time of 1 day and is made of B with a 3 day lead time. The requirement for A is 30 units for the 30th of July. Now the system is asking for B on the 27th of June. The planners need B until the 30th of july and they need the start planned date on 27th of july. One month before we need it.

Is it possible while running MRP to consider only the lead times of the part and not the time of the routings?

achavezf
25th May 2007, 00:46
Sorry We are using LN FP3

grleluc
1st June 2007, 16:38
HI achavezf,
You have to use the prameter fixed lead time horizon in Plan Items session (cprpd1500m000).

Look at the help topics, it will be helpfull.

achavezf
1st June 2007, 21:59
Hi,
Thank you very much for your help.
It is working. That was an easy one.
Regards