Dear all,

we are using BaaN c4 mcr and PCS module.The question is regarding the budgetted amount of the calculation parts in the Project Budget Module. In tipcs0110m000 the Purchase Price of the calculation parts are entered whose quantities are defined in tipcs1110m000 as net quantity. After Budget Calculation we expect that the amount of the calculation parts in tipcs1550m000 will be "Purchase Price X Quantity" . But it isn't.

Do you have any idea about the amount field in tipcs150?

sukesh75
17th May 2007, 10:31
It looks like the calculation is based on the price * 1 unit of the item purchased. I dont use the budget system but going by how baan calculates the cost prices of customized items(estimated and actual) in pcs module, they are all based on one unit of the item ordered or manufactured...

sk