hsaenz
8th May 2007, 21:59
How do you make BaaN automatically set the Planned Production Orders to Forward Planning?

Jennyadr
5th June 2007, 13:09
In ERP LN 6.1 ,the planned production order can be set forward ,by change it manually in the planned production order.I use to change it manually for the end item.After i transfer it to the shop floor, then i generate again for the component.
But for automatically to change it forward, it can not.
Since for the forward planning method, we are the one who decide the start date.

Hope it helps

hsaenz
5th June 2007, 17:56
Thanks for your reply

Renegade
15th September 2008, 12:05
Is there a way to change Planning method that is now Forward to Backward? The order status is Active.

It is disabled now.

pinkey
15th September 2008, 13:43
We can define the workload parameter cpwlc2101m000,Parameter as forward planning for getting planned prod order in forward planning method

Renegade
15th September 2008, 16:09
Work flow is disabled in EP Parameters;

Anyways... seems there is no way to change status as of now, atleast in 5c, I need for manage the RePlanned Delivery date by adding a dummy operation and put cycle time that will drive the date.