1st November 2001, 11:57
When MRP is generated, the planned MRP purchase orders always use Planning Method "Backward". It looks like the system use "Backwards" by default, this also appears on MRP Production Orders, SFC Orders and Planned PRP Orders.

Is it possible to force MRP/PCS to plan Forward? I have tried to find a parameter, but I can't find it.

Sturla

invensys user
1st November 2001, 12:03
Which version of Baan are you using?
In Baan V you can (f.e. in workload control) indicate to use back or forward planning. If you are using Baan IV, it is one of the standard parameters, let me know, I can trace it for you

sturla
1st November 2001, 14:03
Hello Invensys User!

We ar using Baan IV c4, SP 6+

Sturla