HI All:
Have a question to ask your help.

when I run Generate Order Planning(this session is cprrp1210m000), when I go to the "Option" label, two options are invisible,
the two options is :
Use Bottom-Up Item Selection
Use Top-Down Item selection
I don't know how to let them can visible.
I wish the expert can give me some help .

Thanks!

DFisch
22nd March 2007, 13:28
Which SW-release do you have: LN FP2?
IN FP2: if you use the new function "use-up-material" then bottom-up and buttum-down planning is not available. This issue is solved in FP3...
regards Dirk

hujiehujie
23rd March 2007, 02:29
Thanks for DFisch. My version is FP2,but my other company have the two option for the same FP2 version.

such as I have two company, the nubmer is 100,200, and 100 is invisible, and 200 is visible.

DFisch
23rd March 2007, 13:50
so please read my first comment carefully:
In Session tccom0100 (impl. sw-components) on form "concepts" is a switch "Use up and alternative materials".
If this switch is "yes" you cannot use bottom up and bottom down planning. This is solved in FP3.

hujiehujie
24th March 2007, 03:24
Hi DFisch: Now is ok, thanks a lot !