14th March 2007, 20:20
We have reached the max of 999 sequence numbers for a single project within the session tipcs3140 - table/field tipcs340.sern. Does anyone have options for continuing to apply general project costs to this project?
Thanks in advance.
P
sukesh75
17th March 2007, 07:12
Since you already ran out of sequence number for this project.. i guess what you could is to change the Project Type of the current project to "Subproject" and then create two additional projects, one(another subproject) to record general cost and the other(Main project) to act as the parent to these two subprojects(use session Maintain Project Structure:{tipcs2115m000})...
If you do go ahead with this solution, please dont forget to close all three projects(subprojects: first, main project: last) if you want the costs to hit your accounts...
There might be another option i.e to pass general cost entries directly in one of the finance module sessions.. but i am not sure which...
sk