Anil Menezes
14th February 2007, 07:49
Without unit effectivity , can we trace the progress of the sales order i.e prodn order status, purchase order status and the expected date of completion of the sales order
atender prasad
17th February 2007, 16:06
anil kya bekar ke question kartey ho, yeh to main personally hi bata deta.
atender
tritonbaan
19th February 2007, 04:29
Use pegging functions avaiable in EP modules.
Or an easier method is check the session planned inventory transactions. Normally the production orders of the end products should be created when your sales guys want to check the status.
tyagi.ravinder
21st February 2007, 14:30
Project code and unit effectivity, I think, are only the solid things that can be used for traceability between sales order and production order. Anything else will only puzzle you.
Anil Menezes
22nd February 2007, 10:34
Many thanks ravinder, your comments have been very helpful.
Navin Tenani
27th February 2007, 08:45
Hi,
Can you please help me in understanding the concept of Unit Effectivity. In case any document is also available with you, please mail the same to navintenani@yahoo.com.
Thanks
Navin Tenani
Anil Menezes
3rd April 2007, 10:16
Dear Navin
If you are using ERP Ln then the help is the best possible documentation.
The process is clearly explained in the help.
ashu2814
12th November 2008, 13:49
hi,
Can u forowrd me any document regarding unit effectiviy.If,do u have.