wilsonphilips
5th December 2006, 23:23
Hi Everybody:


Some one can help me:

Our situation is:

We work with BaanIVC2 and the Manufacturing Projects (tipcs).

Now we have the problem that when we run the project costing, each time the system run costs for all the project again and not for only the part that we sell.

That problems causes that our accounts have bad data.


Any ideas, must be parameters or may be a system bug?.

thanks for your help.

filipd
14th December 2006, 14:45
Hi,

The cost price is always calculated for the entire project. This is standard functionality.
I'm not sure about BaanIVc, but in BaanV, if you are using standard items in your project, you could "freeze" the cost price from the project parts session.
Also, you could try working with main- and sub-projects and then calculate the cost price for the sub-project only.

Regards.

sukesh75
17th December 2006, 12:40
Are you referring to the running of session Calculate Cost Price by Project?
If so what cost are you talking about, Estimated or Actual?

sk

wilsonphilips
27th December 2006, 17:10
Hi all:

Thanks for the replyes,

Do you know if exits any customization, that enable the posibility for calculate costs of a project's part, not for all the projects?.


thanks for tha advice.

We are running actual costs.


Thanks

sukesh75
28th December 2006, 07:30
Try the main project - sub project scenario.


sk