2nd November 2006, 10:06
Dear friends...
I have problem about my MRP.
We use BaaN 5.0 c.
We have implemented MRP based on capacity (master based planning + work load control).
One case that baan haven't given answer to me is:
Lead time :safty time, outbound time, and extra time is not working in master based planning.
Let's say: customer order fall on 15 Nov 2006.
Marketing departement will input on 15 nov. But production schedule + capacity requirement planning must be started on 14 nov. So, we need lead time to move the palnning start on 14 nov.
Can anyone help me to do this, BaaN has not given solution for this case?
Thank you very much for your help.
Best Regards,
Sigit
I have problem about my MRP.
We use BaaN 5.0 c.
We have implemented MRP based on capacity (master based planning + work load control).
One case that baan haven't given answer to me is:
Lead time :safty time, outbound time, and extra time is not working in master based planning.
Let's say: customer order fall on 15 Nov 2006.
Marketing departement will input on 15 nov. But production schedule + capacity requirement planning must be started on 14 nov. So, we need lead time to move the palnning start on 14 nov.
Can anyone help me to do this, BaaN has not given solution for this case?
Thank you very much for your help.
Best Regards,
Sigit