LittleJohn
15th August 2006, 08:06
Hi,
This is in Baan Vc.
Item B is one of the components in the BOM of Top level Item A.
I have 1 (one) production order of 10 pcs for Item B.
I have 10 production orders of 1 pc each for the top level item A.
When reschedule messages are created by 'EP', I see 10 reschedule(in/out) messages, for different dates, for the production order of Item B. (because of its ten-time requirement in Item A).
How can I avoid these many reschedule messages. Is it possible to see only 1 message, in this scenario ? What parameters would i use on reschedule in/out signal type in the "Signal Types by Planner" (cprao1110m000) session ?
Which other parameters would need to be set.
Thanks for your time and help.
Regards
LittleJohn
This is in Baan Vc.
Item B is one of the components in the BOM of Top level Item A.
I have 1 (one) production order of 10 pcs for Item B.
I have 10 production orders of 1 pc each for the top level item A.
When reschedule messages are created by 'EP', I see 10 reschedule(in/out) messages, for different dates, for the production order of Item B. (because of its ten-time requirement in Item A).
How can I avoid these many reschedule messages. Is it possible to see only 1 message, in this scenario ? What parameters would i use on reschedule in/out signal type in the "Signal Types by Planner" (cprao1110m000) session ?
Which other parameters would need to be set.
Thanks for your time and help.
Regards
LittleJohn