Sigit Taylor
4th August 2006, 05:48
Dear All,
We use BaaN 5.0 c service pack 14. I have case about BaaN Forecasting (demand and sales planning).
My case is about set up forecasting. We need past data for forecasting.
In Baan enterprise planning/demand and sales planning, we have set all the parameter need and also in scenario. My problem is:
1. Because BaaN system especially forecasting take past data form item master plan. How to set up that the item master plan will have past data at least 4 months.
2. We need only one data for each month resulted by the forecast. But, in fact, BaaN always advice for each period (my set up => 1 period = 1 day).
How to limit that the data resulted by the forecast is only 1 data per month?

Please look at attachment for detail of this case,
Thank you very much.

Best Regards,

Sigit