LittleJohn
2nd August 2006, 05:11
Hi,
This scenario is in Baan Vc.
I have a production order for 10 pcs. At Operation 50, I reject 6pcs and Report Operation Complete (ROC) Oper 50. I'm left with 4 pcs on Operation 60. Operation 60 is a Subcontracting Operation. I Generate a Subcontracting Purchase order using the standard session... and It creates a Pur Ord for 4 pcs. I send out the 4 pcs for outside processing and recieve them back in.
At Operation 70, I release that I should not have rejected 6 pcs... but rejected only 1 pcs.
Baan will let me go and Un-ROC the operations until operation 50, correct the reject Qty to 1 and complete 9 pcs.
Here is my problem. I've already created a Pur Order for 4 pcs. Is it possible to create another purchase order on the same operation for these remaining 5 pcs. Baan stops me from creating another Pur Ord for the same operation.
How do I work around this. I tried adding a new position to the old Pur Order for 5 pcs, But I cannot receive it back into the prod order.
(Dont want to pursue the option of creating a dummy item on a manual Pur order, add it to the prod order BOM and receive it into stock and issue it to the prod order).
All help is appreciated. Thanks
Regards
LittleJohn
This scenario is in Baan Vc.
I have a production order for 10 pcs. At Operation 50, I reject 6pcs and Report Operation Complete (ROC) Oper 50. I'm left with 4 pcs on Operation 60. Operation 60 is a Subcontracting Operation. I Generate a Subcontracting Purchase order using the standard session... and It creates a Pur Ord for 4 pcs. I send out the 4 pcs for outside processing and recieve them back in.
At Operation 70, I release that I should not have rejected 6 pcs... but rejected only 1 pcs.
Baan will let me go and Un-ROC the operations until operation 50, correct the reject Qty to 1 and complete 9 pcs.
Here is my problem. I've already created a Pur Order for 4 pcs. Is it possible to create another purchase order on the same operation for these remaining 5 pcs. Baan stops me from creating another Pur Ord for the same operation.
How do I work around this. I tried adding a new position to the old Pur Order for 5 pcs, But I cannot receive it back into the prod order.
(Dont want to pursue the option of creating a dummy item on a manual Pur order, add it to the prod order BOM and receive it into stock and issue it to the prod order).
All help is appreciated. Thanks
Regards
LittleJohn