Question
17th July 2006, 21:57
Hello, there is mfg item with negative inventory and the delivery date of the production order is two days later. If I run PRP today, will the system rescheduling the delivery date to today's date?
Thanks,
Martin Jung
18th July 2006, 08:33
If the production order is already released, the system will come up with a rescheduling message, not with an rescheduling action. It's up to the planner to make the final decision.
Regards,
Martin
Question
18th July 2006, 17:06
If the production order is already released, the system will come up with a rescheduling message, not with an rescheduling action. It's up to the planner to make the final decision.
Thank you for your reply. The problem is that the company is running regenerate PRP every weekend. We got the rescheduling message to move in the date to Saturday (which is not a working date) for all the production orders with negative inventory. The planner is confused since it is not a working date. Should Baan check the calendar first?
Thanks,
naabi0
18th July 2006, 18:39
Is there safety time on that item?
Martin Jung
19th July 2006, 08:12
Should Baan check the calendar first?
Yes, company calendar is always taken into consideration, regardless to the safety time or any other item parameter. Did you check your company calendar (by company/work center) already?
Regards,
Martin