10th May 2006, 04:32
Good Day!

Customized item P1-Item1 has been manufactured under project P1. The item was manufactured in excess and is available in stock. Now we want to sell this item to a customer under project P2. I know it is not possible to mention P1-item1 and link project P2 in the sales order. What are the various ways to accomplish the sale of this item under project P2?

Thanks,
srikarthy

jdboer
10th May 2006, 11:54
create a PRP warehouse order from project P1 to project P2
(or transfer the project-stock on forehand from project to a warehouse with a PRP order warehouse to project)

Navin Tenani
18th May 2006, 09:47
Hi,

The solution provided seems to be very much perfect. Hope the prob is resolved.

Rgds

Navin Tenani