Jason Patte
28th March 2006, 18:59
I have a generic routing on an item, this item takes 80 mins to complete. It takes 3 men to complete this task.
However the production order costs are only 80 mins, BaaN doesn't seem to multiply the labour costs by 3.
Simple, not really. Any advice would be appreciated.
Man Occupation = 3
However the production order costs are only 80 mins, BaaN doesn't seem to multiply the labour costs by 3.
Simple, not really. Any advice would be appreciated.