VilasoorRavi
26th March 2006, 15:20
In session ticst0101m000, Enter Material Issue for Production Orders, there is no date specified. Does it mean that, if I want to enter consumption data for, say, 23rd March, 2006 today i.e. 26th March, 2006, I will be unable to do so? In other words, is the date of data entry taken as the date of material issue for Production orders?

rgds,

Ravi Kumar

Hutje33
29th March 2006, 11:48
Hi,

When components in your PBom are related to operations, the estimated materials will be allocated time-phased based on the thus generated production planning.
Also in case extra demands is entered in ticst0101m000 and you connect the new lines to present operations, the transaction date in tdinv150 will be created accordingly.