Jennyadr
24th March 2006, 08:41
Hi everybody,
How do you doin :) ?
I hope in great conditions.
I use SSA ERP LN 6.1 fp 1
1. Alternative Item
I have set an alternative item with interchangable checked (replacement unchecked). I thought that if i use interchangable, when i create the production order which the standard item stock level is zero, it will automatically trigger the alternative item to the estimated materials in the production order.May be I have missed something?
2. Work Center
We make one work center consist of 5 different machine (different process for the same product) ,and different operators for each machine (machine 1= 4 operators, machine 2 = 5 operators ,..etc) , the total operators = 25.
If I input in the work center : number of machine = 5, and the number of operators = 1 (because we only define one employee for the work center in the system) ==> is it correct?
Is it effect when I generate order planning? (I set in the critical capacity planning = man capacity )
How SSA calculate the costing for the production order which use the machine in this work center?
sorry , i really confuse, im new in ssa.
Many thanks for your consideration .
Cheers,
Jenny:D
How do you doin :) ?
I hope in great conditions.
I use SSA ERP LN 6.1 fp 1
1. Alternative Item
I have set an alternative item with interchangable checked (replacement unchecked). I thought that if i use interchangable, when i create the production order which the standard item stock level is zero, it will automatically trigger the alternative item to the estimated materials in the production order.May be I have missed something?
2. Work Center
We make one work center consist of 5 different machine (different process for the same product) ,and different operators for each machine (machine 1= 4 operators, machine 2 = 5 operators ,..etc) , the total operators = 25.
If I input in the work center : number of machine = 5, and the number of operators = 1 (because we only define one employee for the work center in the system) ==> is it correct?
Is it effect when I generate order planning? (I set in the critical capacity planning = man capacity )
How SSA calculate the costing for the production order which use the machine in this work center?
sorry , i really confuse, im new in ssa.
Many thanks for your consideration .
Cheers,
Jenny:D