Is there any way to rough capacity plan, production plan or schedule before BOMs are maintained?

I think the answer is no, but I want to hear from you all.

Paul P
8th February 2006, 05:39
For Rough Cut Capacity Planning (RCCP), you'll only need to plan the critical operations. So, for orders of completely new manufactured product, you can make a mock up routing containing ONLY the critical operations, generate Bill of Critical Capacities (BCC) from it, and run RCCP. What do you think?
Rgds,
Paul