luann_s
13th January 2006, 22:22
We use Baan IVc4

I understand there is a setting to set a 'wait' period between purchasing and production. Currently Production Orders can be scheduled to be started the same day material for the order is due (delivery date on Purchase Order). How can I set up an offset.


luann_s

rocky6
15th January 2006, 05:17
It's been a while since i worked with BaanIV, but I believe if you put a value (in days) in the Safety Time field on the purchased item(s) you will get the buffer you're looking for.

Hutje33
16th January 2006, 10:06
Indeed you might consider setting safety time for relevant items.
For Purchase items MRP will use the buffer at the end of the throughput time, so it will generate orders x days before normal order date
For manufactured items, the end date of the advices will also be x days before normal del.date, so it is used as "slack" at the end of the order.