9th December 2005, 08:11
I have this problem and hope someone can advise.
By setting an item as phantom (either with tipcs021.cpha or tipcs022.cpha), I will move the routing steps (tipcs023) for this item to higher level and will expect the lead time of this item to be zero.
Unfortunately, executing session “Generate Planned PRP Order” failed to update the lead time to zero and the lead time remain as it is.
I understand BaaN does not accept item with zero lead time but for phantom item, I think BaaN should.
At this moment, we need to manually update the lead time to zero.
I am wondering is there a better way for this.
By setting an item as phantom (either with tipcs021.cpha or tipcs022.cpha), I will move the routing steps (tipcs023) for this item to higher level and will expect the lead time of this item to be zero.
Unfortunately, executing session “Generate Planned PRP Order” failed to update the lead time to zero and the lead time remain as it is.
I understand BaaN does not accept item with zero lead time but for phantom item, I think BaaN should.
At this moment, we need to manually update the lead time to zero.
I am wondering is there a better way for this.