we want to change the capacities for specific workcenters per week. Because of that we think to set the parameter calendar type in session tirou0100m000 from "by company" to "by workcenter".

Should I maintain a calendar for every workcenter, or only for workcenters with different capacities ? What happens with workcenters without own calendars (taking calender for ZZZ) ?


Ralf

Hutje33
7th November 2005, 09:43
Not sure but it used to work as follows:
when no dedicated calendar is present for a certain work center, Baan should pick up the ZZZ-standard calendar. Therefore you don't need to specify calendars for each single wc. Proper testing is preferred, since the calendar area was not known for being one of the most solid components.......

ralf wingert
7th November 2005, 09:58
thanks for your reply.

I tested it for one working center and it seems Baan is working the described way. If no special calendar is found, Baan takes the calendar for working center ZZZ.