Is there any way to determine what items in the BOM for a production order are sent to a subcontractor? I've look around at a lot of the Manufacturing tables, but I don't see how to tie them together.

blueboy
11th May 2005, 05:07
Hi,

Unfortunately, it's the operation that is sub-contracted in Baan not the components. However, I guess if you linked the sub-con components to the sub-con operation via the BOM, you should then be able to report on components by sub-con operation.