23rd March 2005, 12:42
Hi

I have a problem in Process module of baan. We have a Mfd process item A whose formula contains an item B (Mfd .process item)as material. Item A has a routing say from opn 10 to opn 60. Now item B has one dummy task in its routing and its formula has materials(5 components) from say positions 10 to 50

Now I want to attach the routing operations of item A to the materials(components) of item B( psfrm011.opno) for time phased issue of inventory.

Is this possible in any manner.

Thanks in Advance.

rudra01

frank99
1st April 2005, 10:48
You can link operations only to components of the same process item (A). If you have to issue material belonging to item B time-phased to the production of item A the question is, do you really produce item B? In this case it would not be possible to issue the same material to item A since it changed already from the previous process.