donnie
22nd October 2004, 11:00
Hi, I'm working with BaanERP. Is there anyone who can help me in understanding how BaanERP calculates the field "Ordee lead time". Which datas are used?
Thanks
Donato

Paul P
11th January 2005, 06:31
Hi Donato,

Sorry for the late reply. Are you talking about the order lead time that you're suppose to specify in item data? If yes, it's a value that the planner think should be the fixed production run length to produce this item. This is applicable if the planner think that it's unnecessary to calculate production run length in detail during planning and simplification such as this will do

Rgds,
Paul

vijayb
13th January 2005, 16:32
[QUOTE=vijayb]Hi, I'm working with BaanERP. after generating networking planning,i tried to print it but not happpen ,suggest me is it possible if so how?

vijayb