Hope someone can provide some advice.
Due to urgency, I need to have partial delivery out of a production order. Original planned quantity of the production order is let say 10 pc. Come to operation 40, which is a long lead time operation, we need to send whatever quantity (let say 4 in this case) that has been reported complete to the next operation. This next operation, 50, is a subcontracting operation whereby we need to generate Purchase order(PO) to our supplier.
When I use session tisfc2250m000 to generate the PO to the supplier, the PO genarate will have a quantity of 10 instead of 6. This is still ok as we can overwrite the quantity in the PO.
Imagine now the remaining 6 pc from operation 40 also reported complete. My question is how am I going to generate the PO for the 6 pc for operation 50? BaaN don't allow us to create 2 subcontracting PO for the same operation for the same priduction order.
Hope someone can advice.
Due to urgency, I need to have partial delivery out of a production order. Original planned quantity of the production order is let say 10 pc. Come to operation 40, which is a long lead time operation, we need to send whatever quantity (let say 4 in this case) that has been reported complete to the next operation. This next operation, 50, is a subcontracting operation whereby we need to generate Purchase order(PO) to our supplier.
When I use session tisfc2250m000 to generate the PO to the supplier, the PO genarate will have a quantity of 10 instead of 6. This is still ok as we can overwrite the quantity in the PO.
Imagine now the remaining 6 pc from operation 40 also reported complete. My question is how am I going to generate the PO for the 6 pc for operation 50? BaaN don't allow us to create 2 subcontracting PO for the same operation for the same priduction order.
Hope someone can advice.