LittleJohn
6th June 2004, 01:11
This is in BaanVc.
I'm trying to change the Start Remainder Date on the Last operation of Production Order Planning. This date when changed in the planning, also affects the (Re)-Plan Delivery Date on the Production Order.
I'm trying to achieve this using FS. I'm able to update the date in most cases.. but in some cases... FS comes back with an error as mentionend below
"
Cal 001 , 001 , 001, Av. Type PR01 - \n Insufficient Availability defined-A00000017Sales Order/Pos A00000034/10
"
(The production Order is still in Released status.. and the last operation St. Rem Date is 07/14/2004. This am changing to 05/01/2004).
But If I go to that planning and manually change the date, it changes it for the same above order and operation, without any error/mesg at all.
What am I doing wrong here... and what does the above error mean ?
I dont know if this question might be for the FS forum.. but I guess its more related to Manufacturing.
Cheers
I'm trying to change the Start Remainder Date on the Last operation of Production Order Planning. This date when changed in the planning, also affects the (Re)-Plan Delivery Date on the Production Order.
I'm trying to achieve this using FS. I'm able to update the date in most cases.. but in some cases... FS comes back with an error as mentionend below
"
Cal 001 , 001 , 001, Av. Type PR01 - \n Insufficient Availability defined-A00000017Sales Order/Pos A00000034/10
"
(The production Order is still in Released status.. and the last operation St. Rem Date is 07/14/2004. This am changing to 05/01/2004).
But If I go to that planning and manually change the date, it changes it for the same above order and operation, without any error/mesg at all.
What am I doing wrong here... and what does the above error mean ?
I dont know if this question might be for the FS forum.. but I guess its more related to Manufacturing.
Cheers