22nd March 2004, 21:19
Im looking for some feedback as to how other organizations are tracking production reject scrap/rework in BaanIVc3.
Our process is as follows:
Currently when an item is at an operation and is questionable it is rejected from the production order. We then inventory adjust the qty to a Quality Hold area (non net able warehouse) that we have setup. We have a side application that we enter in the production order, operation, and reject qty. We use this for tracking purposes
This inventory sits in the QA warehouse until they decide that the parts can be reworked or scrapped. If they are scrapped then the qty is inventory adjusted off of the QA warehouse. If they can be reworked, then a rework order is put in the system, the inventory is adjusted back into a standard location and pulled into the rework production order.
Some issues that we have:
1. It can take QA months to decide if the inventory can be reworked or not. This causes problems with the Finance Department as they are trying to balance production order etc. When its rejected from the production order they take a hit, and they do not know when or if there will be a reversing transaction (rework order).
2. Its difficult to track all of the rework orders etc.
Thanks
Chris Boudreau
IMT Corporation
Our process is as follows:
Currently when an item is at an operation and is questionable it is rejected from the production order. We then inventory adjust the qty to a Quality Hold area (non net able warehouse) that we have setup. We have a side application that we enter in the production order, operation, and reject qty. We use this for tracking purposes
This inventory sits in the QA warehouse until they decide that the parts can be reworked or scrapped. If they are scrapped then the qty is inventory adjusted off of the QA warehouse. If they can be reworked, then a rework order is put in the system, the inventory is adjusted back into a standard location and pulled into the rework production order.
Some issues that we have:
1. It can take QA months to decide if the inventory can be reworked or not. This causes problems with the Finance Department as they are trying to balance production order etc. When its rejected from the production order they take a hit, and they do not know when or if there will be a reversing transaction (rework order).
2. Its difficult to track all of the rework orders etc.
Thanks
Chris Boudreau
IMT Corporation