Paul Eden
21st November 2003, 22:19
We are considering a change to our current structure and I wasn't sure of the response to a question that was posed to me.

If we have a multi / multi environment how / where / when does the PRP get run.

We will be loading the sales orders into a master company and then (hopefully) move these out to the various logistical companies. I'm thinking that the upper level (saleable) items will have a warehouse code attached which will send the line to the correct logistical company and then we would run PRP in that company.

Can anyone shed some light on this scenario.

Kind regards,

Paul Eden
Teknion Furniture Systems
Toronto, Ontario

cjssidhu
25th December 2003, 09:44
Try sub-project functinality. Attach the relevent company for the sub-project and then run PRP in each logistic company for the sub-project.
rgds