19th August 2003, 12:23
Hi,
I have a little problem in doing planning in Baan ERP using EP module.
Let's say that I have the following process:
A - B - C - D (each of them are different work centers and the item code changes after every process)
Suppose I'm running a simulate master-plan/order session and the resulting planned orders show (thru Resource Master Plan session) that work center C is the bottleneck one and some periods are overloaded. So I maintain the planned orders for work center C and make manual date adjustment. After done with them, I change the planned order status to "Firm-Planned"
The problem is, how to make the planned orders' date in the preceding ( A & B) and subsequent ( D) workcenter to follow the changes I already made in workcenter C?
If I simply run the simulate master-plan/order session again, it won't do. The dates just don't match with the one I manually adjust.
Anyone has any solutions please?
Thanks a lot,
hendra
I have a little problem in doing planning in Baan ERP using EP module.
Let's say that I have the following process:
A - B - C - D (each of them are different work centers and the item code changes after every process)
Suppose I'm running a simulate master-plan/order session and the resulting planned orders show (thru Resource Master Plan session) that work center C is the bottleneck one and some periods are overloaded. So I maintain the planned orders for work center C and make manual date adjustment. After done with them, I change the planned order status to "Firm-Planned"
The problem is, how to make the planned orders' date in the preceding ( A & B) and subsequent ( D) workcenter to follow the changes I already made in workcenter C?
If I simply run the simulate master-plan/order session again, it won't do. The dates just don't match with the one I manually adjust.
Anyone has any solutions please?
Thanks a lot,
hendra