Hai Everybody,

I am working in BaaN 4c.
I am facing difficulty in rework-production orders.

Whenever failure happends, immediately we raise a rework-production order. But we are using Supply Chain Scheduler for planning purpose and also its re-scheduling period is one week.
Now problem is rework-production orders are going to plan after one week only. But I want to start rework-production orders immediately.
Is it any other way to do and account rework without rework-production order.?

regards
raju