FransG
9th July 2003, 15:25
In BaanERP it is possible to have a main and sub work center setup. With respect to that there are a couple of questions I like to raise.
The following might sound theoretical and I admit it is, but I like to know the real business practises for this/these scenario(s).
Suppose the following data setup:
There is one main work center called MAIN.
There are two sub work center that have MAIN as their main work center. These are called SUB1 resp. SUB2.
Work center SUB1 has one operator and two machines.
Work center SUB2 has also one operator and one machines.
Questions:
What about setting up work center MAIN?
Does this imply that work center MAIN has 2 operators and 3 machines (i.e. aggregating SUB1 and SUB2)?
What if it is modelled as one operator that handles both SUB1 and SUB2?
Or is it possible to have one operator and one machine that are unique entities next to SUB1 and SUB2?
In production planning it is possible to have SUB1 and SUB2 as the work center to do the work, but it can also be done on work center Main. The utilization data for SUB1 and SUB2 can be determined pretty easily, but how about the utilization of the main work center? Does one aggregate the man and machine capacities of the sub work centers?
Normal capacity. The normal (man) capacity of a work center is calculated as number of operators multiplied with the basic week capacity as defined at the work center. What is the normal capacity of a main work center? Does the same rule apply or does one have to aggregate?
The following might sound theoretical and I admit it is, but I like to know the real business practises for this/these scenario(s).
Suppose the following data setup:
There is one main work center called MAIN.
There are two sub work center that have MAIN as their main work center. These are called SUB1 resp. SUB2.
Work center SUB1 has one operator and two machines.
Work center SUB2 has also one operator and one machines.
Questions:
What about setting up work center MAIN?
Does this imply that work center MAIN has 2 operators and 3 machines (i.e. aggregating SUB1 and SUB2)?
What if it is modelled as one operator that handles both SUB1 and SUB2?
Or is it possible to have one operator and one machine that are unique entities next to SUB1 and SUB2?
In production planning it is possible to have SUB1 and SUB2 as the work center to do the work, but it can also be done on work center Main. The utilization data for SUB1 and SUB2 can be determined pretty easily, but how about the utilization of the main work center? Does one aggregate the man and machine capacities of the sub work centers?
Normal capacity. The normal (man) capacity of a work center is calculated as number of operators multiplied with the basic week capacity as defined at the work center. What is the normal capacity of a main work center? Does the same rule apply or does one have to aggregate?