halvorn
19th February 2002, 12:22
Hi,
I wonder what actions are updating this field.
I guess it is in the sessions ticst0101m000 (Enter Material Issue For Prod Orders) and tisfc0110m000 (Maintain Estimated materials). Maybe when the "Allocated Field" changes, if that's the case: when does this field Change ?

Best regards Halvor

:rolleyes:

Jim Ritchie
19th February 2002, 18:19
the date is controlled by the operation to which the material is attached, if no operation then it is the start of the work order, recheduling or moving operations/ work orders changed the allocation date