7th July 2003, 14:56
Can I generate/produce a sub contracting purchase order manualy. I want to add the rate of the item.

can any body send me documentation on sub contracting procedure.

Regards

Paul P
8th July 2003, 05:37
Dear Tushar,

Unfortunately you can't generate BaanERP subcontracting PO manually. You can only generate it from a BaanERP production order that you'd like to subcontract. Once the PO generated, you can also change its rate to any rate you'd like

However, if you'd like to manually make a PO representing a subcontracting activity, then you can just make a PO of type cost

Rgds,
Paul