13th August 2004, 18:54
Hi everyone!

I have 2 vrc's in one server, one of the vrc has a group of companies in which the calendar has been changed to start on wednesday as the first day of the week. The change affected the company in the other VRC. Should I have all calendars the same? or is there a way to solve the problems?

BEst regards, Gabriela

NPRao
13th August 2004, 20:19
The first day of the week is defined at a company/package combination level.

So you have to relink your VRCs to a new package combination and then change the first day of the week.

gabymore
13th August 2004, 20:56
Rao, thank you so much