Dear,
I have two questions about advance payment.
1.
If I maintain advance payment through "tfcmg2100s000"
and select maintain button, then " Assign unallocated/advance payment to invoice" session(tfcmg2106s000) is appeard.
So I select one advance payment transaction and select "automatic" then finalizing.
The result is printed like this;
"Dr. N/A / Cr. (+) Cash
Dr. N/A / Cr. (-) Advance Payment"
I wonder what is that meaning and why this journal entry is happened, only credits are appeared?
2.
Once an advance payment is entered and finalized,
after then I receved back the advance payment amount
from Supplier.
So I want to enter the transactions like;
debit - cash
credit - advance payment
How can I do?
Thanks for your help.
Best regards,
NA YOUNG HOON
I have two questions about advance payment.
1.
If I maintain advance payment through "tfcmg2100s000"
and select maintain button, then " Assign unallocated/advance payment to invoice" session(tfcmg2106s000) is appeard.
So I select one advance payment transaction and select "automatic" then finalizing.
The result is printed like this;
"Dr. N/A / Cr. (+) Cash
Dr. N/A / Cr. (-) Advance Payment"
I wonder what is that meaning and why this journal entry is happened, only credits are appeared?
2.
Once an advance payment is entered and finalized,
after then I receved back the advance payment amount
from Supplier.
So I want to enter the transactions like;
debit - cash
credit - advance payment
How can I do?
Thanks for your help.