parames
20th December 2002, 10:51
Hello list,
I'm using baan Iv and informix database.
Normally when we do 'maintain receipt', the data will flow to integration tables. And all the amount with foreign currencies( i.e. USD) will be converted to local currencies amount (RM).
My problem is, there are two to three PO's where when i do 'display integration transactions by project / order' , the amount is still in foreign curency (USD).
In the Maintain PO, the currency is USD and also in maintain supplier the currecy is USD.
So, where is the problem.??? Please do guide me..
Thanks a lot .
Best Regards,
Parameswari Sellaparma
I'm using baan Iv and informix database.
Normally when we do 'maintain receipt', the data will flow to integration tables. And all the amount with foreign currencies( i.e. USD) will be converted to local currencies amount (RM).
My problem is, there are two to three PO's where when i do 'display integration transactions by project / order' , the amount is still in foreign curency (USD).
In the Maintain PO, the currency is USD and also in maintain supplier the currecy is USD.
So, where is the problem.??? Please do guide me..
Thanks a lot .
Best Regards,
Parameswari Sellaparma