armiewei
27th November 2002, 07:37
Hi, there is one question which has long time confused me.
I am using BaaN IVC4, in maintain routings, we set task and run time for certain operation, and task was link to operation rate, and in the maintain routings , it clearly shows that man occupation
was 2, but when we calculate standard operation cost in Item master, its result is runtime * ( labor rate + machine rate + overhead rate ), it ignores the man occupation and machine occupation , I don't know which session's setting let BaaN calculate in this way.
What I believe the correct way is run time *
( man occupation * labor rate + machine occupation * machine rate + overhead rate )
Can anybody explain to me why BaaN do in this way ?
Regards
I am using BaaN IVC4, in maintain routings, we set task and run time for certain operation, and task was link to operation rate, and in the maintain routings , it clearly shows that man occupation
was 2, but when we calculate standard operation cost in Item master, its result is runtime * ( labor rate + machine rate + overhead rate ), it ignores the man occupation and machine occupation , I don't know which session's setting let BaaN calculate in this way.
What I believe the correct way is run time *
( man occupation * labor rate + machine occupation * machine rate + overhead rate )
Can anybody explain to me why BaaN do in this way ?
Regards