larkin_jack2
12th June 2002, 18:18
Does anyone know about Production Surcharge Integrations?

Specifically I need to know what accounts should be debited and credited

Thank-you

julisb
13th June 2002, 08:59
Hello Jack,
generally said you book like that:
- debit : Work-in-Process
- credit: To surcharge cover

But it depends which you want to keep about the kind of production surcharge so the credit account might be more differentiated.

Good luck,
Juli

larkin_jack2
14th June 2002, 16:51
Juli, does this sound correct?

Debit : WIP
Credit: Efficiency Variance - Material

The reason I am using Efficiency Variance - Material, is because the surcharge item is freight.

Thank you!

larkin_jack2
14th June 2002, 17:40
Juli, does this sound correct?

Debit : WIP
Credit: Efficiency Variance - Material

The reason I am using Efficiency Variance - Material, is because the surcharge item is freight.

Thank you!

julisb
14th June 2002, 23:21
sounds ok
Regards, Juli

larkin_jack2
17th June 2002, 20:11
Thank you!

larkin_jack2
17th June 2002, 21:09
Thank you!