Hi,

The finance user would like to create another cost center for Thailand branch.
Currently we got maintain one cost center (A) and under this, we got sub cost center. the concern is we will create another new cost center, let say B, then
a) where to maintain the new cost center and
b) got any possiblities this cost center will affect the existing gl

Pls advise...
any ideas are most welcomed.

Many Thanks

Regards
april5098

cborge
13th March 2007, 02:37
if you create a new cost center this will be afect GLD

Sai_krishna
14th March 2007, 01:19
How are u maintaining ur cost centres. Normally cost centres are linked to dimensions i.e one of the dimension types will be cost centres.

Regards