14th December 2006, 06:14
HI, all.
i have a problem inconsistency between P-bom and E-bom.
when copying E-bom to P-bom,select Overwrite Existing P-bom;If there exists an item in P-bom ,but E-bom doesn't include this item,how to deal with this problem?
As i know,Estimated material line in PO are decided by P-bom,not E-bom,so,how to react to the change of E-bom?
thanks.

zcgecho
14th December 2006, 06:38
sorry,my problem is caused by myself.
i have added a new line in p-bom,so when i finalize engineering data and check Overwritting exsiting p-bom,it can't overwrite the new line manually
i added .