Hi!
I have been working on LN6 integration set-up and need some help in Production integration. How do the entries flow . as I understand entries are as below:
On Issue
Entry 1
IDT 10060052 Warehouse Issue/Issue
Interim Transit Debit
Raw material Stock Credit
Entry 2
IDT10014052 Production/Issue
WIP Debit
Interim Transit Credit
Now are these entries correct.
How is purchase price variance booked.. ?
What are the entries for Post FG to inventory and Batch close??
Regards,
H
I have been working on LN6 integration set-up and need some help in Production integration. How do the entries flow . as I understand entries are as below:
On Issue
Entry 1
IDT 10060052 Warehouse Issue/Issue
Interim Transit Debit
Raw material Stock Credit
Entry 2
IDT10014052 Production/Issue
WIP Debit
Interim Transit Credit
Now are these entries correct.
How is purchase price variance booked.. ?
What are the entries for Post FG to inventory and Batch close??