30th July 2006, 15:06
Dear Experts,

After preparing the Purchase order what are all the steps to be done to make the payments to the supplier and integration.

Please advice.

Thanks in advance.

mig28mx
31st July 2006, 20:05
1.- Generate PO to the provider.
2.- Receipt the goods.
2.1.- Costs runs the Integration transactions to Accountable baches.
3.- Pass to ACP the provider invoice.
4.- ACP will reconciliate the PO lines and approves the invoice
5.- CMG will generate the payment.

Hope this help.