sweber
8th March 2004, 20:25
Hello,

We use PCS. We have been using it for years. We have shipped, invoiced and closed a zillion projects. When I run this session for a range of projects, I get no data in selection.

I am wondering why.

Our PCS parameter is set to Actual cost and the report is too.

Are there any flags missing on the project or SO that I don't know about?

Any information would be appreciated.

Thanks

Kaibou
10th March 2004, 12:00
...archieved integration data + PCS date in the meantime ?

sweber
11th March 2004, 18:22
There has not been any archiving or compressing of any integration tables or PCS data at all.

sweber
23rd March 2004, 22:54
Anyone else have any ideas? Or does anyone else have success with this session?

Koen Roks
3rd May 2005, 16:40
Are you working in a multi-site company structure?