mbezdek
19th November 2003, 00:18
We are on 5.0c and running the Cost Price Calculation, ticpr2210m000, and then running the Actualize Cost Prices, ticpr2220m000. We have about 450,000 items in our item master, and about 1/3 of these items will have a cost price change. We have tried running these both wide open and narrowed down to specific item groups. We have seen the Cost price calculation take approximately 3 hours, which is probably ok given our volume. However, the Actualization session is running for 40-45 hours, which seems to be extremely long. Has anyone else seen long run times for cost actualization? Has anyone come up with any alternative ways of handling this type of volume?

jlalgue
21st November 2003, 10:38
Hi,

¿Do you have installed solution 133915?
It improves performance in session ticpr2220m000.

mbezdek
24th November 2003, 15:13
we are on 5.0 so that one won't work unfortunately. There is actually a solution, 134080, for 5.0 that fixes the actualization processing time..