WE HAVE DESIGNED TWO WAREHOUSES IN OUR BUSINESS PROCESS IE., MAIN STORES & SPARE PARTS STORES. MAIN STORES IS A NETTABLE WAREHOUSE WHEREAS SPARE PARTS STORES IS NON NETTABLE.THERE WILL BE SALES ORDERS WHICH WILL HAVE PURCHASE ITEMS AND ALSO MANUFATURED ITEMS. THESE ITEMS WILL HAVE TO BE DISPATCHED FROM SPARE PARTS STORES ONLY AFTER COMPLETION OF THE PRODUCTION. WHEN WE RUN MRP, SYSTEM IS NOT GENERATING THE PLANNED PRODUCTION ORDERS.THIS MAY BE DUE TO THE FACT THAT SPARE PARTS STORES IS A NON NETTABLE WAREHOUSE.
COULD U PLEASE SUGGEST HOW TO HANDLE THIS PROCESS ?
IS THERE ANY OTHERWAY OF HANDLING THE DEMAND OF MANUFACTURED ITEMS OF A NON NETTBALE WARE HOUSE IN BAAN ?